Site investigation
Approved document C, Site preparation and resistance to contaminants and moisture, suggests that the extent and level of site investigations needs to be tailored to the type of development and the previous use of land.
The approved document suggests that site investigations should consist of four well-defined stages:
- Planning stage: Setting clear objectives for the site investigation, including scope and requirements, which enable it to be planned and carried out efficiently and provide the required information.
- Desk study: Reviewing historical, geological and environmental information about the site.
- Site reconnaissance (a walkover survey): Identifying actual and potential hazards and the design of the main investigation.
- Main investigation and reporting: Including intrusive and non-intrusive sampling and testing to provide soil parameters for design and construction.
Site investigations should include:
- Susceptibility to groundwater levels and flow.
- Underlying geology, and ground and hydro-geological properties.
- Identification of physical hazards.
- Identification of methane and other gases.
- Determining an appropriate design.
- Providing soil parameters for design and construction.
Where a site may be affected by contaminants, a combined geotechnical and geo-environmental investigation should be considered and remediation maybe necessary.
It may also be necessary to notify findings to regulatory authorities, for example:
- Where contaminants are found that had not been previously known about.
- In planning applications.
- In relation to waste management and the protection of water quality and resources.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.